Helix Controls

Project Controls Suite

Client Dashboard · Overview

Mega Residential Compound — Phase 1

Data Date: 30 Sep 20264 Blocks · 1,240 Units · 36-Month Programme
Active — Minor Delays

Overall Physical Progress

64%

Planned 68% · Variance −4%

Planned
68%
Actual
64%

Schedule Performance Index

0.94

Behind schedule · 17 days slip

Cost Performance Index

1.02

Under budget · EAC favourable

Budget vs Actual Cost

SAR 1.84B

Actual SAR 1.16B · 63% drawn

Committed
71%
Spent
63%

Interactive 4D BIM Simulation

Schedule-linked construction sequence · drag to orbit, scroll to zoom

Initialising 3D viewport…

Data Date

Sep 2026

Phase · Finishes

MEP fit-out, façade & internal finishes

Model

4 Blocks · LOD 300

IFC linked to P6 WBS

TimelineMonth 9 of 12
M1M3M5M7M9M11
SubstructureM1–M3
SuperstructureM4–M8
FinishesM9–M12

Earned Value S-Curve

PV vs EV vs AC (cumulative %, 12 months)

Phase Progress

Planned vs actual completion by phase

Critical Milestones

Baseline vs forecast against Level 1 programme

MilestoneBaselineForecastStatus
Enabling Works Complete15 Feb 202612 Feb 2026Completed
Block A – Foundations Signed Off30 Apr 202604 May 2026Completed
Block D – Structure Topping Out22 Sep 202609 Oct 2026Delayed
MEP First Fix – Blocks A/B18 Nov 202602 Dec 2026Delayed
Façade Installation Start05 Jan 202705 Jan 2027On Track
Practical Completion – Phase 128 Jun 202712 Jul 2027At Risk

Delay Analysis & Risk Alerts

Live feed from weekly progress review

  • MEP material delivery delayed by 2 weeks

    Chilled water pipework (Blocks C & D) — critical path impacted.

    CriticalProcurement·3 days ago
  • Concrete pour productivity below baseline

    Superstructure Block D achieving 82% of planned cycle rate.

    HighConstruction·6 days ago
  • Façade shop drawings pending consultant approval

    11 days in review — float consumed on Finishes predecessor.

    MediumEngineering·1 week ago
  • Summer working-hour restriction

    Midday ban Jun–Aug modelled: 4% productivity loss absorbed.

    LowPlanning·2 weeks ago

Demo dataset — figures are illustrative and not linked to a live P6 database.